Industrial and Trade Agreements

Activities and Milestones, Asia

Country

Subject

Current Status

Korea

- Project for implementing quality management system for manufacturing products in Egypt in cooperation with the Industrial Control Authority

$2 million are allocated for the project implementation
Starting Date: March 2002
Completion Date: March 2004

 

- Action plan for establishing the Industrial Technology Center (s) (TCs) in Egypt

$300,000 are allocated for the study on TCs regarding their objectives, funding, organizational and legal structure and Korean experts are currently in Egypt for the project implementation.
Expected inception report: end of March 2002.
Expected Date of Completion: September 2002

 

 

 

Japan

- Upgrading  Shubra El-Kheima Technical Training Center

JICA approved to allocate $8 million for the development.
Starting Date:2002
Duration: 3 years

 

-  Experts for developing Shubra El-Kheima Maintenance Center
 

The Ministry requested three experts a year for developing the center in the fields of training, textile, and planning.
Starting Date: 27th of March 2002
Completion Date: March 2003

 

- Quality expert for the Egyptian General Organization for Standardization and Quality Control

Will be arriving on the 27th of March 2002
Completion Date: March 2003

 Activities and Milestones, Europe

Country

Subject

Current Status

Germany

- Establishing Technology Competence Center and Staff Training Institute

DM 3 million has been allocated for establishing the centers.
Starting Date 2002
Duration: 3 years

Italy

- Establishing "Service and Technology Specialized Center" in the Egyptian Stone Sector
- Establishing Training School for wood furniture and furnishing Industry

Two studies were submitted by the Italian counterpart for establishing the centers.
They were revised and the Italian counterpart was contacted to plan for further steps of implementation.

Spain

1.Technical Assistance
2.Training Programmes
3.Transfering technology and legislative information
4.Consultancy in quality management
5.Consultancy in environmental issues
6.Assistance in packaging techniques

Funding: 290,000 EURO
Starting Date: 2002
Duration: 4 Months.

 

 Activities and Milestones, International Organizations

Country

Subject

Current Status

UNIDO

presented a Country Service Framework (CSF) consisting of 6 components namely:
1. Industrial Competitiveness
2. Industrial Governance
3. Energy & Environment
4. Industrial & Technology Promotion
5. Industrial Information
6. Small Scale Leather based Industries

The CSF is currently under revision to match the requirements and strategic objectives of the MITD.

ILO

Traditional Industry Enhancement Project

The ILO agreed to provide a Traditional Industry expert for a month to assist the ministry to formulate a detailed work plan for the modernization of the traditional industry sector

Activities and Milestones, International Organizations (cont.)

Country

Subject

Current Status

AIDMO

Establishing Regional Center for developing and modernizing traditional industry.

A preliminary proposal study for the establishment has been prepared by AIDMO
 

Islamic Bank

Funding two studies for generating electricity from El-Maghara Coal and  manufacturing phosphate acid from phosphate concentrate found in Abu Tartour ($200,000/study)

Alternative proposals are being prepared

World Bank

 

- providing databases for the experts participating in the industrial modernization programmes.
- Skills enhancement project

Undergoing preparations

 

 